Intro Columbus at 9th And High
U.S.’s Tallest Mass Timber Student Housing Rises in Columbus
Client
Harbor Bay Ventures
Project Location
Columbus, OH
Area
242,000 SF
Services
Architecture, interiors
Mass Timber Performs
INTRO Columbus topped out in September 2026, roughly ten weeks ahead of its original schedule, a pace the project team attributes to off-site prefabrication and tight field coordination. The mass timber superstructure is tracking to save 1,128 metric tons of carbon compared to an equivalent concrete and steel structure. Sourcing timber domestically from Alabama, rather than from Europe, also cut the project’s transport-related carbon emissions by approximately 55%, reinforcing mass timber’s performance on both schedule and sustainability.